Friday, November 6, 2015

Testing the lights. Looks like we're ready to play night games.

Monday, November 2, 2015

SCE energizing the panel 

Tuesday, September 22, 2015

Construction is done. Ready to get envergized by SCE. 

Monday, September 21, 2015

Panel being installed 

Friday, September 18, 2015
Finish Major field, trench for center pole, pour pad for panel and sidewalk 

Thursday, September 17, 2015
Trench for center pole 

Wednesday, September 16, 2015
Trench service area were panel for panel 

Tuesday, September 15, 2015

Monday, September 14, 2015

Trenching Minor Field behind home plate 

Friday, September 11, 2015

Trenching Major Field behind home plate 

Thursday, September 10, 2015

Trenching the Major Field 

Wednesday, September 9, 2015
Trenching Minor outfield 

Tuesday, September 8, 2015
Trenching Minor outfield 

Friday, September 4, 2015

Lights ready to go up

Poles getting raised
Video of Major left field pole going up
Video of Minor right field pole going up

Minor Field

All the light poles are up 

Thursday, September 3, 2015
Wired and ready to go up 

Wednesday, September 2, 2015

Pouring cement for the Major 3rd base pole

Pouring cement for the Minor 1st base pole

Pouring cement for the center pole

Assembled poles. Cement hose (left picture) was around 225' long.

Tuesday, September 1, 2015

First hole being dug

Pole ready for cement

Center pole ready

Digging the last hole (click the picture to watch video)

Monday, August 31, 2015

Truck arrived this morning

Construction crew offloading equipment

Storing away the lights

Putting all the precast foundations in place

Precast foundation for center pole was a challenge

...but they made it through