Light Project
Friday, February 23, 2016
Video clip from the City of Torrance Sportsdesk
Friday, November 6, 2015

Testing the lights. Looks like we're ready to play night games.
Monday, November 2, 2015

SCE energizing the panel
Tuesday, September 22, 2015

Construction is done. Ready to get energized by SCE.
Monday, September 21, 2015

Panel being installed
Friday, September 18, 2015
Finish Major field, trench for center pole, pour pad for panel and sidewalk
Thursday, September 17, 2015
Trench for center pole
Wednesday, September 16, 2015
Trench service area were panel for panel
Tuesday, September 15, 2015
Rain
Monday, September 14, 2015

Trenching Minor Field behind home plate
Friday, September 11, 2015

Trenching Major Field behind home plate
Thursday, September 10, 2015

Trenching the Major Field
Wednesday, September 9, 2015
Trenching Minor outfield
Tuesday, September 8, 2015
Trenching Minor outfield
Friday, September 4, 2015

Lights ready to go up

Poles getting raised
Video of Major left field pole going up
Video of Minor right field pole going up

Minor Field

All the light poles are up
Thursday, September 3, 2015

Wired and ready to go up
Wednesday, September 2, 2015

Pouring cement for the Major 3rd base pole

Pouring cement for the Minor 1st base pole

Pouring cement for the center pole

Assembled poles. Cement hose (left picture) was around 225' long.
Tuesday, September 1, 2015

First hole being dug

Pole ready for cement

Center pole ready

Digging the last hole (click the picture to watch video)
Monday, August 31, 2015

Truck arrived this morning

Construction crew offloading equipment

Storing away the lights

Putting all the precast foundations in place
Precast foundation for center pole was a challenge

...but they made it through